All metro switches installed and removable railway platforms replaced

In the weekend of 18 and 19 December 2021, we installed the final two switches in the metro tracks. At the same time, 1,000 sq. m. of floor was replaced from the removable railway platform for tracks 1 and 2. The work went smoothly.
reizen-en

Overnight works on the metro tracks

Until the end of 2021, we are working on the metro tracks from Amsterdam Zuid station to just past RAI. We are adding five switches. This will cause some disruption. The work is required in order to create a larger work site between the metro tracks at Amsterdam Zuid station.
reizen-en

The next steps at Amsterdam Zuid station

Three roof sections are now in place under the tracks for the new pedestrian passageway at Amsterdam Zuid station. The construction sites look neat and tidy, but appearances can be deceptive. By popular request, here is a preview of the next phases of the work.
reizen-en

Creating space for new metro platforms

Amsterdam Zuid station is set to have new metro platforms, between the existing passageway and the new passageway currently under construction. We will need to make space for them. So, how will this be done and how will it affect passengers and local residents?
wonen-en
reizen-en
werken-en

Nieuw-Zuid consortium to build public transport hub at Amsterdam Zuid

The construction consortium Nieuw-Zuid (Mobilis, Boskalis and Van Gelder) has been awarded the contract for modernization and expansion work at Amsterdam Zuid station. The first phase of the contract was signed on 26 August.
wonen-en
reizen-en
werken-en

Work at Amsterdam Zuid station went smoothly last weekend

Last weekend (21-22 August 2021), we took a major step in the construction of the second pedestrian passageway underneath Amsterdam Zuid station. The work involved installing two enormous concrete roof sections into place for the new passageway. Everything went like clockwork.
reizen-en

Amsterdam Zuid station fully prepared for mega-operation

The preparatory work has been completed. Two concrete structures, weighing a total of more than two million kilogrammes, have been lifted out of their formwork and moved several centimetres to test whether everything is in order. The result: the real work can now begin in earnest.
reizen-en

19-23 August: major construction work at Amsterdam Zuid station

Between the evening of Thursday 19 August and the morning of Monday 23 August, there is likely to be disruption at Amsterdam Zuid station due to major construction work. There will also be fewer train and metro services than usual, and local residents can expect a significant amount of freight traffic going to and from the site.
reizen-en
werken-en

Shifting two million kilogrammes with millimetre precision

Right next to Amsterdam Zuid station on Saturday, 21 August, we will be placing two roof sections of the new station passageway into their final position. In total, they weigh more than two million kilogrammes. ‘This work requires centimetre, or even millimetre, precision.’
reizen-en

Creating the third roof section of the Brittenpassage

Fifty mixing trucks containing ten cubic metres of concrete each were needed to create the third roof section for the new pedestrian underpass at Amsterdam Zuid station on 9 June 2021. ‘It was quite a logistical challenge’, says Frank van Klaren of construction consortium ZuidPlus.
reizen-en

Successful Easter weekend of work on Zuidasdok

A new piece of the foundations for the extra station passageway, a wider platform and a bend in railway track 4. That’s what we have to show for 100 hours of work over Easter weekend. On the morning of Tuesday, 6 April 2021, the trains and metros resumed normal services.
reizen-en

Photo update: work on foundations for extra station passageway on schedule

The foundations for two roof sections for the additional passenger tunnel at Amsterdam Zuid station are now in the ground. On Saturday, 3 April 2021, the reinforcement cages were put in place and filled with concrete. So far, the work has run according to schedule. Here’s a brief impression of the work.