skip to main content
Article archive

Article archive

reizen-en

New schedule announced for Zuidasdok

The major Zuidasdok project now has a new schedule. The original plan was for a single contractor to work on all of it. The project has now been divided into parts, some of which will be happening simultaneously. So, what can you expect?
reizen-en

Tendering process launched for De Nieuwe Meer interchange

The tendering process for the reconstruction of the De Nieuwe Meer interchange, including the bridges over the river Schinkel, has been officially launched. The project is part of the Zuidasdok project and aims to improve traffic flow on the A10 Zuid.
reizen-en

Environmental permit for station upgrade undergoes intensive preparation

The definitive design for the Amsterdam Zuid public transport hub has been completed. We will shortly be submitting an application to the North Sea Canal Area Environmental Service (‘Omgevingsdienst Noordzeekanaalgebied’) for an environmental permit. This has been preceded by intensive preparation.
reizen-en

Creating the third roof section of the Brittenpassage

Fifty mixing trucks containing ten cubic metres of concrete each were needed to create the third roof section for the new pedestrian underpass at Amsterdam Zuid station on 9 June 2021. ‘It was quite a logistical challenge’, says Frank van Klaren of construction consortium ZuidPlus.
reizen-en

Testing the stone tiles for the new pedestrian passage: coffee, cola and ketchup

Three new test areas consisting of stone tiles will be installed at Amsterdam Zuid station this summer. Various types of grey stone tiles will be monitored over the coming year to see how they respond to wear and usage. Tests have already been done to see how they cope with spills and stains such as coffee, cola and ketchup.
reizen-en
2

New Amsterdam Zuid station will be much easier to access

The new Amsterdam Zuid station will have many more stairs, escalators and lifts leading to the platforms than the existing station. That means no more crowds of people on the stairs and escalators leading to the platforms. The new access routes have been designed by Frank Bouwman and his colleagues – a much more complex challenge than you might think.
reizen-en

The Zuidasdok project – a complex jigsaw puzzle

‘Each of the roof sections that need to be placed over the new pedestrian passageway at Amsterdam Zuid station is unique’, explains planning engineer Jim Kerssens. The construction consortium ZuidPlus is currently working on the third roof section – there will be seven in total.
reizen-en
werken-en

Zuidasdok report and shortfall estimate

Outgoing Minister Cora van Nieuwenhuizen and deputy mayors Victor Everhardt and Egbert de Vries have updated the House of Representatives and Amsterdam City Council on Zuidasdok and the estimated financial shortfall.
reizen-en

Successful Easter weekend of work on Zuidasdok

A new piece of the foundations for the extra station passageway, a wider platform and a bend in railway track 4. That’s what we have to show for 100 hours of work over Easter weekend. On the morning of Tuesday, 6 April 2021, the trains and metros resumed normal services.
reizen-en

Photo update: work on foundations for extra station passageway on schedule

The foundations for two roof sections for the additional passenger tunnel at Amsterdam Zuid station are now in the ground. On Saturday, 3 April 2021, the reinforcement cages were put in place and filled with concrete. So far, the work has run according to schedule. Here’s a brief impression of the work.
reizen-en

Fully prepared for over 100 hours’ work over Easter weekend

We are hard at work preparing for the long working weekend over Easter. That's when will be making the foundations for two new roof sections for the additional passenger tunnel at Amsterdam Zuid station – the Brittenpassage. We are currently assembling the caterpillar cranes.
reizen-en

Railway track 4 at Amsterdam Zuid station goes ‘bendy’

Starting at 20.00 on 1 April 2021, we will be working on Zuidasdok night and day until 05.00 on 6 April. One of the jobs will involve putting a bend in railway track 4 to enable platform 3-4 to be widened. ‘A real improvement,’ says Tjeerd Dierckxsens.
  1. Previous
  2. 1
  3. 2
  4. 3
  5. Next