Launch of tender for A10 Zuid tunnel

The tendering process for the construction of a motorway tunnel at the centre of Zuidas has been launched. We are diverting part of the A10 underground in order to extend Amsterdam Zuid station. This is all part of the Zuidasdok project.

Demolition work continues on car park under A10 Zuid

We are currently in the process of partially demolishing the former Atrium car park underneath the A10 Zuid. This work is necessary because this is where the entrance to the additional station passageway – the Brittenpassage – will be. All of the concrete removed will be reused.

Parnassusweg closed for two months for traffic exiting city

Because the metro viaduct across Parnassusweg is being widened, the carriageway in the direction of Amstelveen will be close to cars and buses between 24 July and 1 October 2023. However, slow traffic can continue to use Parnassusweg during the works.

Preparatory work on A10 tunnel next to WTC

Starting on 31 July, we will be doing preparatory work for the future A10 tunnel in Matthijs Vermeulenpad. For the safety of passers-by, this often-used route, leading from Beethovenstraat to Zuidplein and the station, will be closed completely.

Are you ready for the eight-day closure of the A10 Zuid?

There’s not long to go now: from the evening of Saturday, 5 August until the morning of Monday, 14 August, the A4 and A10 Zuid will be closed from the Badhoevedorp interchange to the S109 RAI access road. We are certainly ready for it. But is everybody else in Zuidas?

Don’t miss the Zuidas Zomer Keet

Starting on 20 July 2023, the Zuidas Zomer Keet (Zuidas Summer Shack) will be back in Gustav Mahlerplein. In it, we’ll tell you all about the summer works at Amsterdam Zuid station, but there’s also much more: guided tours, workshops and tuktuk rides. Make sure you don’t miss it!

Replacement of Rozenoordbrug to be part of Zuidasdok project

The replacement of the southern Rozenoordbrug on the A10 Zuid will be part of the reconstruction of the Amstel interchange, one of the Zuidasdok projects. ‘The city of Amsterdam is developing. We need to be sure we have the capacity to keep pace with it.’

1 July: installing sheet piles at Amsterdam Zuid station

In the last week of June 2023, we had to halt sheet piling work west of Amsterdam Zuid station due to the instability of the metro track. We will complete the work on Saturday 1 July, after which we will repair the track.

Zuidasdok report on the second half of 2022

On 27 July 2023, Amsterdam City Council and the Dutch House of Representatives were updated on progress on the Zuidasdok project in the second half of 2022. The report provides a valuable insight into the status of the work at the end of 2022.

Zuidasdok Routing Decision changes approved

On 22 June 2023, Mark Harbers, Minister of Infrastructure and Water Management approved the 2023 changes to the Zuidasdok Routing Decision (‘Tracébesluit Zuidasdok (wijziging 2023)’). This involves an amendment to the routing decision originally agreed in 2016. The relevant documents are available for viewing from 23 June until 3 August 2023.

3 July: meeting to discuss works in Prinses Irenebuurt area

A lot of construction work is taking place between Amsterdam Zuid station and Prinses Irenestraat. In the upcoming period, there will also be works in and around the station. On 3 July 2023, we are organising a walk-in meeting at the Thomaskerk to update you on what is happening.

The architectural vision behind Zuidasdok

On National Architecture Day (‘Dag van de Architectuur’), we will be focusing on our own area. Rather than singling out one of Zuidas’ acclaimed buildings, we will take a look at the infrastructure. What is the architectural vision behind Zuidasdok?