Starting in September 2023, we will spend a year working on the entrance to the new Ravel residential district: Maurice Ravellaan, with space for pedestrians, cyclists and plenty of green areas. We are also digging an actual canal, complete with bridges to the AFC sports fields.
On the site of the former temporary courthouse at Fred. Roeskestraat 55, there are plans to develop a building with offices and housing. The draft zoning plan for this development is now open for consultation until 18 October 2023. A walk-in evening has been scheduled for 21 September.
In the weekends of 9-10 and 23-24 September 2023, there will be disruption for travellers wishing to access the metro or railway from Zuidplein. The station entrance will be closed for up to 10 minutes on a regular basis (every two hours). There will also be noise disruption.
Henk Appels will shortly be standing down as Building Manager at the Atrium in Strawinskylaan. He sees a Zuidas that is becoming increasingly busy: homes are being built, and there will be a tunnel and a new passageway in the future. ‘Ultimately, we all need to work together.’
For two weekends in September 2023, there will be major traffic disruption on the south side of Amsterdam. Between 8 and 11 September and between 22 and 25 September, the A10 Zuid in the direction of Schiphol and The Hague will be closed from the Amstel interchange to the S108 VUmc access road.
Are you interested in organising a film festival, theatre production or concert in Zuidas? It could be possible thanks to a new subsidy scheme especially for cultural events. Private individuals and professional organisers can apply at any time during the year.
The station entrance in Parnassusweg was open again on Monday 21 August – two weeks earlier than scheduled. We removed some underground cables and pipelines in order to create space for the future motorway tunnels for the A10 Zuid.
The summer of 2023 is about more than just the regeneration of Amsterdam Zuid station. At the De Nieuwe Meer interchange, TriAX is hard at work conducting all kinds of investigations in preparation for the reconstruction of the interchange.
From Saturday, 19 until Sunday, 27 August, we are working on one of the metro platforms at Amsterdam Zuid station. This is creating space for the renovation of the existing station passageway. For a nine-day period, the metro will run a modified service.
On the evening of Wednesday, 9 August, it was finally time for the big event: shifting two sections of the roof for the Brittenpassage, the second passenger tunnel at Amsterdam Zuid station, into position millimetre by millimetre. It also attracted a great deal of interest from the press and public.
Until September 2023, we are carrying out major works in Parnassusweg on both the existing and a new metro viaduct. This will involve a lot of sheet pile work. During that time, we will also be temporarily closing the A10 in the direction of Schiphol/The Hague on four separate occasions.
On 7 and 8 August 2023, dozens of construction workers were working around-the-clock at Amsterdam Zuid station. Preparations were being made to move two huge roof sections for the second passenger tunnel – the Brittenpassage – into position. Take a look at what happened.