Between 19 and 23 February 2024, we will be removing the Carve playground equipment from Beatrixpark. It was becoming less of a source of fun and enjoyment and an increasing cause of nuisance. Zuid city district is now considering what will replace it. You are welcome to contribute any ideas you may have.
On Thursday, 1 February 2024, the new GVB Service & Tickets desk in the existing passageway at Amsterdam Zuid station will open. The existing desk has to be removed to make space for the renovation of the passageway.
Plans for Kop Zuidas to have a residential care centre for former homeless people on plot K will not go ahead. For the centre to be affordable, at least 30 housing units were needed. There is not sufficient space for that. The tender procedure for the plot will be in the second quarter of 2024.
The second passenger tunnel at Amsterdam Zuid station is beginning to take shape. In the space of four months, we have removed huge amounts of sand from underneath the A10, railway and metro tracks and the broad contours of the new passageway are now becoming visible. In this series of photos, we take a look back.
The broad contours of the second passageway at Amsterdam Zuid station became visible. The existing passageway was also renovated. Numerous construction projects were completed. We also put together a great summer party. All of that – and much more – was 2023 in Zuidas.
The contracting parties for the Zuidasdok project have updated Amsterdam’s municipal council and the Dutch House of Representatives regarding progress on Zuidasdok in the first six months of 2023.
Underneath the roof of the additional passageway at Amsterdam Zuid station, we are doing much more than just digging. Alexander Bor from the Nieuw-Zuid Construction Consortium tells us all about it. ‘By the start of 2024, the southern side of the Brittenpassage will have reached the right depth.’
We have reached yet another milestone for the new passageway at Amsterdam Zuid station. The intensive construction work on the roof is gradually coming to an end. We are pouring some 240 cubic metres of concrete for the seventh and final roof section of the new Brittenpassage
From a patchwork of paving to a green oasis. The campus square at Vrije Universiteit Amsterdam (VU Amsterdam) is currently undergoing a metamorphosis, which is set to make it the heart of the campus once again. ‘We were assigned the job of making the square more attractive. That’s not too difficult.’
Sharp-eyed locals will have already spotted it: after some delay, work on The Art Bridge (‘De Kunstbrug’) across De Boelegracht has resumed. Additional investigations while preparing the foundations led to some delay, postponing the completion date until May 2024.
In a lively canteen at AFC football club, the Zuidas Sustainability Award was presented for the second time on 9 November 2023. A panel of expert judges selected winners across various different themes. Around a thousand people also voted for the Public Award.
Zuidas is working on plans for the Verdi neighbourhood, part of which includes the northern zone of IJsbaanpad. This is being given a new use. From 9 November 2023, the draft zoning plan that will make this development possible is open for consultation.