Construction of GVB fast charging station on schedule
Construction began in December 2025, and the substructure of the new fast charging station has now been completed. The next phase is the construction of the structure above ground. Cyclists and pedestrians will continue to be diverted until the end of 2026.
Construction of GVB fast charging station on schedule
Construction began in December 2025, and the substructure of the new fast charging station has now been completed. The next phase is the construction of the structure above ground. Cyclists and pedestrians will continue to be diverted until the end of 2026.
Plan for 0 parking spaces for new Zuidas offices requires further study
Adjusting the parking standard for car parking at new office developments in Zuidas requires further research. Public participation shows that the so-called 0-norm for car parking spaces leads to mixed responses. We are therefore starting a follow-up study into the effects and possible scenarios.
Transportation of ‘Schinkelbrug bridge’ from Friesland to Amsterdam
From Friday, 24 April 2026, Zuidasdok will transport a new section of the Schinkelbrug bridge from Friesland to De Nieuwe Meer over the course of five days. As the bridge deck is too large and heavy for road transport, the entire journey will take place by water. The transport can be followed live.
27 April – 5 May: major disruption on the A4, A10 and at Amsterdam Zuid station
From Monday, 27 April at 21.00 until Tuesday, 5 May 2026 at 05.00, we expect significant traffic disruption on the south side of Amsterdam. The A4 and A10 Zuid will be closed at various times. From 28 April, there will be no train services to and from Amsterdam Zuid station for one week.
New layout for the Beethovenstraat–Ravellaan junction
From 22 April to mid-July 2026, we will be working at the junction of Beethovenstraat and Maurice Ravellaan. During this period, we will complete the final layout of the junction. The pedestrian and cycle crossing will be closed, and motorists will also experience disruption.
Four days and three nights of piling at De Nieuwe Meer junction
From Tuesday, 28 April to Friday, 1 May 2026, we will carry out piling works at the De Nieuwe Meer junction. This is part of the widening of the A10 Zuid. The piling will take place both during the day and at night and may cause noise disturbance.
Weekend 24-27 April: A10 Zuid-A10 West connection closed
From Friday, 24 April 2026 at 22.00 until Monday, 27 April at 05.00, the road connecting the A10 Zuid to the A10 West (in the direction of Leeuwarden/Zaanstad) will be closed. This could increase your journey time by up to 30 minutes.
We have just completed a busy weekend closure, both at our work sites and on the road. At Amsterdam Zuid station, we removed old platform canopies, while at the Schinkelbrug, we continued construction of the new northern bridge. The A10 Zuid was closed in both directions.
In the future, the A10 Zuid will be routed underground over a distance of one kilometre. This will create around 100,000 square metres of (largely public) space above ground. Designing this space presents a range of challenges.
In April 2026, construction will begin on Benten in the Kenniskwartier innovation district. Benten will be a residential building with 127 rental apartments for students of DUWO housing corporation. Contractor Plegt-Vos is moving quickly: ‘In 12 months, the building will be complete.’
Until Friday, 24 April 2026, we will plant seven trees in Gaasterlandstraat, alongside the SUD and Zuidoever buildings. This will make the easternmost residential area of Zuidas a little greener.
Installing girders for the new northern Schinkelbrug
During the weekend of 10-13 April, there will be major disruption on the A10 Zuid and at Amsterdam Zuid station. We will, inter alia, be working at the Schinkelbrug bridge, where we will install 26 large girders for the new, northern bridge.
Well-attended information meeting on the widening of A10 Zuid
In the coming years, Zuidasdok will be working on widening the A10 Zuid, including modifications to the De Nieuwe Meer and Amstel junctions. During an information meeting, we provided insight into the plans, the works and the expected disruption.
On the evening and night of Tuesday, 7 April 2026, we will be working on the Beethovenstraat. Two trees will be relocated to make space for a new culvert. Two days later, on the evening and night of 9 April, a further three trees will be removed.
Successful weekend of construction work on flyover
During the weekend closure of 27-30 March 2026, we installed more concrete elements for the flyover at the De Nieuwe Meer junction. And that was not all: we also constructed sand platforms for the large cranes.
10-13 April: major disruption on the A10 Zuid and at Amsterdam Zuid station
From Friday evening, 10 April 2026 at 22.00 until Monday morning, 13 April at 05.00, the A10 Zuid will be closed in both directions. The A4 in the direction of Amsterdam will also be closed. Additionally, on 11 and 12 April, there will be no train services at Amsterdam Zuid station.
Amstel junction: from investigations to design and construction
Since mid-March 2026, we have been carrying out extensive asphalt and soil surveys in and around Amstel junction. We want to gain a better understanding of the substrate. This is necessary to complete the provisional design later this autumn.
Removal of old platform canopies at Amsterdam Zuid station
During the weekend of 10-13 April 2026, we will remove a large part of the old train platform canopies at Amsterdam Zuid station. This marks a milestone in the renewal of the existing passenger tunnel, which is set to undergo a major reconstruction.
Rapid progress towards completion of the Brittenpassage
In 2027, you will enter Amsterdam Zuid station via the new passenger tunnel, the Brittenpassage. The construction site beneath the A10 Zuid is visibly transforming into a passageway with plenty of daylight, an indoor bicycle parking facility and escalators. Take a look.
Redesign of De Boelelaan Midden: share your thoughts (again)
Based on your ideas, we have updated the designs for the new carriageway, the service road and the green spaces along De Boelelaan Midden. From 16 March to 14 April 2026 we would like to update you at several moments and locations. Please drop by and share your thoughts.
31 March: information meeting about works at De Nieuwe Meer junction
As you may have noticed, work on widening the A10 Zuid is in full progress. This involves a number of road closures and sometimes noise disturbance. During an information meeting on 31 March 2026, we will tell you all about the works. You are welcome to attend.
The connection from the A10 South to the A10 West Leeuwarden/Zaanstad will be closed from Friday March 27, 2026 from 10 p.m. to Monday morning March 30 at 5 a.m. (was: Sunday morning 10 a.m.). One lane on the A4 towards Schiphol is also closed.