The opening of the new passenger tunnel at Amsterdam Zuid station also marked the start of a major refurbishment of the old Minervapassage, which will take several years. When it reopens in 2031, it will be much taller, wider and brighter than it is today. But that is still some way off. For now, we need to demolish the existing passageway to make room for the refurbishment.
Coming weeks: clearing out the passageway
Over the next few weeks, we will remove everything from the passageway that can still be reused, including shop fittings and public transport ticket gates, which will be taken away for use elsewhere. Outside the passageway, we will dismantle the pavilions that previously housed Hema, Starbucks, Albert Heijn and Julia’s. This work will not involve any heavy demolition, so residents and nearby businesses are unlikely to notice much disruption.
Demolition work inside the passageway
That will change when demolition work gets under way during November and December. Broadly speaking, we need to demolish everything between the supports holding up the roof along the sides of the passageway. This will involve noisy work, including cutting and breaking up concrete. We will also need to reroute underground cables and pipes, among other things, to ensure that demolition and construction work can be carried out safely, with electrical supplies disconnected.
Noise and disruption
We expect the work to cause noise disturbance in the surrounding area from early November until 21 December 2026. Most of this will be during the day, but there will also be noisy work overnight from Monday, 16 to Tuesday, 17 November and from Tuesday, 17 to Wednesday, 18 November. There will also be noise disturbance during both the day and night on the weekends of 5 and 19 December. In addition, we will close the A10 Zuid in the direction of the A4/Schiphol on Saturday, 19 and Sunday, 20 December to demolish the old metro platforms.
Demolishing the metro platforms
We will also demolish the metro platforms on the eastern side of the passageway over two weekends. These are no longer needed now that the metro platforms have moved to the new Brittenpassage. Demolishing structures both inside and above the passageway is a delicate operation, particularly as metro and train services will continue running overhead for the time being.
Looking ahead
In 2027, we will build a construction access ramp between the metro tracks, running from Beethovenstraat towards the Minervapassage. We will also build an additional section of roof between the northern metro track and the A10 Zuid, allowing the motorway to be moved slightly further south in the future. We previously carried out similar work on the northern side of the Brittenpassage.
Beneath the train tracks on the southern side of the station, we will move the roof into its correct position and height, as we have already done beneath the metro tracks. This will require two of the four train tracks to be taken out of service for extended periods from August 2027 onwards. We will, of course, provide more information about this nearer the time.
Minervapassage
The refurbishment of the Minervapassage is part of the major regeneration of Amsterdam Zuid station, which is needed to accommodate the growing number of passengers. The Minervapassage is expected to be completed in 2031. It will be an impressive 40 metres wide, compared with around 12 metres today. The passageway will also accommodate shops and, among other facilities, a bicycle parking facility.