skip to main content

Underpass beneath Beethovenstraat viaducts closed for four weeks

In July and August 2026, the underpass beneath the road and railway viaducts in Beethovenstraat will be closed to cars and buses for four weeks. During this period, we will be preparing for the construction of the A10 tunnel. Further along, the Beethovenstraat/Ravellaan junction will also be redesigned.

Pile ‘Ryan’ driven into the ground alongside the A10 Zuid

Between the Schinkelbrug and Piet Kranenbergpad, we installed the final pile for the so-called pile mattress. Student Ryan is now permanently connected to the pile after winning a competition that gave him the opportunity to write his name on it.

Dismantling of colourful ‘box building’ alongside the A10 Zuid

The distinctive red-and-blue box building alongside the A10 Zuid is being removed. Over the coming weeks, the containers that make up the temporary building formerly used by Amsterdam UMC-Cancer Center Amsterdam (CCA) will be lifted out. The site is needed for a temporary construction road for the future A10 Zuid tunnel.

10–12 July: A4 and A10 Zuid closed up to S108

During the weekend of 10–12 July 2026, part of the A10 Zuid will be closed in the direction of the A1 Hengelo and the A2 Utrecht. During this closure, we will lift girders into place for the new southern Schinkelbrug bridge. Additional journey times may be up to one hour.

4 July: piling works at the De Nieuwe Meer junction

On Saturday, 4 July, between 07.00 and 19.00, we will be driving piles into the ground on the southern side of the A10 Zuid, between the Schinkelbrug and Piet Kranenbergpad. During the works, one lane will be closed and there will be some noise disturbance.

First residents move into Ravel as Ravelly is completed

Zuidas has gained 75 new social rented homes. The very first residential tower in the new, low-traffic Ravel neighbourhood has now been completed: Ravelly. The first residents will move in this summer.

Weekend work at the Schinkelbrug postponed

During the weekend of Friday, 29 June 2026, we had planned to lift girders into place for the new southern Schinkelbrug bridge. A fault in the traffic signalling system meant that the work could not go ahead and has therefore been rescheduled.

Find us at Mahlerplein this summer

Our Information Centre is relocating. Therefore, we are at our pop-up location on Gustav Mahlerplein. You are welcome from Monday ito Thursday, 11.00 - 16.00.

A recognisable entrance for the Brittenpassage

Over the past few weeks, we’ve been ‘k’nexten’ together a frame of 40 tons of ‘green’ steel, topped with a blue truck tarpaulin measuring no less than 400 square meters. On the evening of 7 July, we hoisted this recognizable 'blue disc' onto the southern facade of the new Brittenpassage. This way, you know where to find the new station entrance, when the Brittenpassage opens on 1 November.
 

Livestreams and videos

  1. webcam
    Amsterdam Zuid station | south side
  2. webcam
    Building the Brittenpassage
  3. webcam
    De Nieuwe Meer junction | south side (at S108)
  4. Video

Construction projects

Amsterdam Zuidas is building a completely new city district, together with developers and contractors. Numerous construction projects contribute to this. Zuidas started out mainly as an office location for leading companies, but now the area wants to be more than that: a complete, unique district where working, living and life come together.

All construction projects