An army of steel fixers from the Nieuw-Zuid Construction Consortium (BCNZ, made up of Mobilis, Boskalis and van Gelder) is currently hard at work connecting thousands of rods of concrete rebar to each other. Over a length of around 100 m, they are building a reinforcement cage for a huge sheet of concrete that will form part of the new roof of the existing passenger tunnel (Minervapassage). The roof section is currently being preconstructed on our work site between the metro tracks, but in the summer of 2024, we will move part of it to the north underneath the most northern metro track (M2, see map). Before that stage is reached, there is plenty of work still to be done. ‘Moving it into position is probably the least complicated part of it all’, laughs Edgar Breedveld, foreman at BCNZ.
Working between two metro tracks
We are replacing part of the existing passageway at Amsterdam Zuid station because, in the future, it will be twice the height that it currently is. In the summer of 2023, we moved the first new roof section for the passageway to its final position between the metro tracks. Right on top of that, we are now building this new, second roof section for the so-called Minervapassage. Later, we will set to work on yet another new roof section. This will then be moved underneath the most southern metro track (M1) in 2025. When that is in position, all of the metro tracks served by the Minervapassage will be at the right height.
Hoses from the concrete pump
When the formwork for the reinforcement of this roof section is ready, the pouring of the concrete will start in early May. Around 400 m³ of concrete will be poured into it. ‘That last piece of the roof section – there between the glass domes – can’t be reached with the concrete pump’, points out Breedveld. ‘That means we’ll have to use hoses attached to the pump to get to it.’ The incoming transport of all the concrete rebar is also being done slightly differently because of the very small construction site: ‘If you lifted it using a normal crane, you’d have to pass right over all the passengers. That’s why we are now using an electric portal crane. It runs across tracks on both sides of the roof section and can lift materials without swinging outwards. That considerably improves safety.’
Seven weeks of work in summer 2024
According to Breedveld, the operation to move the roof section in August 2024 will be the ‘cherry on the cake’ after seven intensive weeks of work in the summer. During that period (from 6 July until 26 August 2024), we will be demolishing the most northerly metro track and platform in order to replace it 2 m higher. This will be done all the way from Parnassusweg to Beethovenstraat. As a result of this increase in height, three of the four metro tracks and platforms will be at the height required for the renovation of the Minervapassage. ‘During this period, we’ll be working 24/7. A lot needs to happen in a short space of time, which is why we’re doing as much advance preparation as possible.’
Demolishing, building supports, moving
So, broadly what is planned for this seven-week period? After the most northerly metro track has been removed, the demolition work will start. We will remove part of the existing roof of the Minervapassage (consisting of concrete girders) and lift off the glass roofs. This will be done in phases in order to limit disruption to passengers – the passageway will actually remain open throughout the seven weeks. We will then build a new support pillar in the passageway. This is required because the new roof section is much longer and heavier than the part of the roof it is replacing. In early August 2024, we will move the sheet of concrete around 35 m to the north. ‘Don’t forget that we’re now building the roof section on top of another roof section – that means that it will soon need to be lowered by a further 2 m’, says Breedveld. ‘It’s a step-by-step process. It will properly take around 48 hours.’
Share article:
Give your opinion
Get in touch with us