The A10 Zuid will gain parallel sections of road in both directions, with the extra lanes intended for local traffic. To achieve this, we are adding an extra bridge on both the north and south sides of the present Schinkelbrug. At a later stage, we will then demolish the existing southern A10 bridge (which carries traffic towards the A1 (Hengelo) and A2 (Utrecht)), which will be replaced by two new bridges. All told, the Schinkelbrug will then have eight bridges: five for road traffic, two for trains, and one for the metro.
Staande Mastroute
During the construction work, the Schinkelbrug must remain open as much as possible for users of the roads, trains, and metro. Moreover, the Schinkelbrug complex forms part of the Staande Mastroute, a waterway that runs from Zeeland via Amsterdam and the IJsselmeer to Delfzijl in Groningen. For this reason, the bridges have to be able to be opened at night too. It is these conditions that make the construction of the new bridges a complicated matter.
18 metre-long piles
The TriAX building consortium (Besix, Dura Vermeeren Heijmans) has come up with a solution. Instead of creating excavation pits in the water, parts of the intermediate supports of the new bridges are being constructed on a building site located on the south-west bank of the River Schinkel. ‘We are first building the extra bridge that will be located on the south side’, says Sander Wedershoven, the TriAX head of work preparation for the Schinkel complex (bridge 9, see map). ‘We start with the foundations. They consist of piles 18 metres in length, which we will insert from a pontoon with a drilling installation. On top of them, we will then build the enormous supports which will eventually carry the bridge deck.’
Gigantic container
TriAX will be constructing the supports partly on the building site. ‘Here, too, space is limited, and to be able to hoist the elements properly, there is a maximum weight in place. That is why we will be pouring the concrete for the individual elements here, which we will then connect up. It will look like a gigantic container, about 2.5 metres high. Once it’s ready, we will use a crane vessel to mount it on the auxiliary construction that is attached to the piles. The reinforcements can then be added, before we fill the container with concrete. From the flat surface this creates, we then build the remainder of the support.’
Supports, girders, moveable part of bridge
In total, we are using this method to build four of these supports on our building site along the river. Two of them are for the extra southern bridge (bridge 9), and two are for the extra bridge on the north side of the present bridge complex (bridge 1). We will be driving the first piles into the ground in the spring of 2025 for the two supports for bridge 9, after which we will be placing the concrete containers on them. The process of pouring the concrete will then begin. The two supports and the remaining components of the lower part of the construction for bridge 9 are expected to be ready by the end of 2025. In 2026, we will be hoisting first the concrete girders that will form the bridge deck, and then the steel deck (the moveable part of the bridge).
Timetable
Bridge 9 is due to be operational in 2027. We will then close the existing southern bridge (bridge 10), with traffic using bridge 9. Bridge 10 will then be demolished and will subsequently be replaced by two new bridges. The existing foundations of bridge 10 will largely be reused for the new bridges. By that time, the construction and testing phase of bridge 1, the extra bridge on the north side, will be at an advanced stage. Its construction will be running several months behind that of bridge 9. Bridge 1 will be the first to be completed definitively – in 2028. Bridges 7, 8, and 9 will be ready in 2031, in accordance with the definitive situation.
Share article:
Give your opinion