skip to main content

During the Whitsun weekend, concrete and reinforcement will be added to around 100 piles that were installed under the metro and train tracks last year. These will form the foundation for two of the seven roof sections that are needed for the new passageway, which will be called the Brittenpassage. Work over the Whitsun weekend was originally planned to take three days, but due to the measures in place to tackle the coronavirus, the ZuidPlus construction consortium can allow fewer people on the site. This is so that everyone on site can continue to keep the appropriate distance from one another. And since fewer passengers are currently using public transport, we are taking the opportunity to extend this period by one day: Friday 29 May.

The roof of the Brittenpassage

Constructing the roof of the future Brittenpassage is a major operation. A total of seven roof sections are required. These need to be installed underneath four metro lines and four railway lines, and in places where a fifth and sixth line for international rail traffic will possibly be built in the future. The plan, after all, is for Amsterdam Zuid station to become Amsterdam’s second major railway station in terms of passenger numbers. The first roof section was already installed under railway tracks 2 and 3 in November. During the Whitsun weekend we will be working on the foundations for the next two roof sections, under railway track 4 and metro track 1.

Demolition of the tram tunnel

In addition to construction of the foundations for the pedestrian passageway, demolition work will also be taking place over the Whitsun weekend. On Friday 29 May, demolition crews will be working in the area to remove the last part of the disused tunnel for tramline 51 to Amstelveen. This work will be completed by 11 p.m. at the latest. We have scheduled quieter work for the subsequent days and nights.

Fewer train and metro services

Although we are working right between the metro and train tracks, and directly adjacent to the station and the highway, the disruption for travellers will be limited. The A10 motorway will remain accessible at all times, and rail and metro services will continue to run, although at a reduced frequency.

Parnassusweg closed

During the nights before and after the Whitsun weekend, many trucks will be bringing construction materials and will need to access the construction site. While the work is going on, too, there will be a constant stream of trucks bringing and taking away building materials, rubble and sand.

For safety reasons, the Parnassusweg heading towards the city centre will be closed to all traffic at three times:

– Overnight from Wednesday 27 May to Thursday 28 May, between 1 a.m. and 5 a.m.
– Between Thursday 28 May at 10 p.m. and Tuesday 2 June at 5 a.m.
– Overnight from Tuesday 2 June to Wednesday 3 June, between 1 a.m. and 5 a.m.

The closure will apply to the section between Mahlerlaan and Strawinskylaan, heading towards the city centre. Cars will be diverted via De Boelelaan, Beethovenstraat and Strawinskylaan. Cyclists and pedestrians will be diverted via the western side of Parnassusweg. On Friday 29 May, there will be additional restrictions for cyclists and pedestrians due to occasional delays on the western side of Parnassusweg caused by work on the new lawcourt building. Traffic controllers will be on site to direct traffic.

Watch live

Of course, as last time, we will make sure that you can watch the work taking place live on our webcams.

Give your opinion

Related articles

Zuidasdok builds work island between the tracks

We are in the process of preparing the construction of two roof sections for the additional entrance to Amsterdam Zuid station. The work will be done between two metro tracks. So how do you build two huge pieces of concrete with only minimal space in which to work? According to Emiel Vergouw, that’s not the only challenge.

Two roof sections for new station passageway in 2021

Work on the additional passenger tunnel for Amsterdam Zuid station, the Brittenpassage, is slowly continuing. In April and August 2021, we will be inserting the second and third roof sections into position. Work outdoors to prepare for this is already starting on 14 September 2020.

Tendering process for new Amsterdam Zuid station starts on 27 October

The tendering process for the renovation and extension of Amsterdam Zuid Station will be officially launched on 27 October 2020. This is according to an announcement made by Zuidasdok today. The preliminary announcement was published on TenderNed on 3 September.
More posts