Plot L2 is located in the Kop Zuidas neighbourhood and, together with The Newton, forms a triangle at the heart of the neighbourhood. The buildings share a courtyard garden. Plot L2 will see the development of a building with around 400 homes (40% social rental housing, 40% midmarket and 20% in the upmarket segment).

There will be a community healthcare centre on the ground floor. This will have space for a GP practice, a physiotherapist or a pharmacy.

Last construction project

The building on plot L2 can be developed when the building on plot K has been completed. This means that L2 will be the last construction project in Kop Zuidas. The building was planned to be completed by the end of 2028. Unfortunately, this is now uncertain due to the overload of the power grid (so-called net congestie).

Planning

  • Start of construction: January 2026
  • Realisation: March 2027