Several modifications need to be made to the Zuidasdok Routing Decision (‘Tracébesluit Zuidasdok’). From 30 November 2022, the draft amending decision will be open for consultation for a six-week period. During that time, anyone can submit an opinion on it.
While the A10 Zuid motorway is closed from 22 July 2022 onwards we are going to be vibro driving 80 sheetpiles into the ground which are needed for the Brittenpassage excavation work later on. This work may cause noise pollution. We invite you to attend the drop-in meeting on Tuesday 5 July.
The major Zuidasdok project now has a new schedule. The original plan was for a single contractor to work on all of it. The project has now been divided into parts, some of which will be happening simultaneously. So, what can you expect?
Until 4 June at the latest, ZuidPlus building consortium will be removing several dead trees that are close to the motorway. The trees pose a risk to traffic because of branches falling off and the possibility of them being blown over by the wind.
The A10 South (Zuid) will be closed in the direction of Schiphol from 23.00 on Friday, 21 February until 05.00 on Saturday, 22 February. This is to enable work to be done for which Schinkelbrug bridge will need to stay open over a long period.
At the end of October and throughout November, roadworks will be conducted at night on and alongside the southern stretch of the A10 orbital motorway (A10 Zuid). As a result, some lanes, connecting roads and slip roads may be closed between 23:00 and 05:00. In such cases, traffic will be diverted. The work will begin on Tuesday 30 October.
On 3 May 2018, the Council of State considered two objections to the Routing Decision for the Zuidasdok project. Due to these objections, this Routing Decision is not yet irrevocable.