From Thursday 1 April 8:00 pm until Tuesday 6 April 5:00 am, we will be working 24 hours per day on the roof of the new passenger tunnel at Amsterdam Zuid station. Although the A10 will remain in use at this time, the work will have a number of consequences for traffic,
The start and end point for the Amsteltram (line 25) will temporarily be located at Eduard van Beinumstraat, on the north side of Amsterdam Zuid station. This has been agreed by the participants in the Zuidasdok project.
At Easter, which for us starts as early as 20.00 on Thursday, 1 April, we will be installing the foundations for two sections of roof for the additional passenger tunnel under Amsterdam Zuid station. This will also involve removing a railway and metro track. It promises to be an exciting job.
In Parnassusweg, a pedestrian crossing is being built between the Atrium and the new courthouse. Work will start on 1 March 2021. It is expected to cause some disruption to traffic. There is also a minor issue with an awkwardly-positioned tree.
Research shows that a considerable amount of the traffic in Zuidas is made up of people delivering parcels. Green Business Club Zuidas is working on a central delivery and pick-up point for parcels. Its plans also involve the use of MyPup electric cargo bikes.
Your bicycle will be removed if you leave it in the street. Around Mahlerplein, scooters parked anywhere except within the designated parking spaces will be ticketed and fines will be issued. Amsterdam Zuid local council plans to introduce these rules later this year, following years of complaints.
On 11 January 2021, we began redevelopment work on the southern section of Mahlerplein. Assistant project manager Doeke Brouwers: ‘It marks a great start to the new year and the end result will already be visible by March.’
The Amstelveen line, tram line 25, was put into use. Officially from Sunday 13 December 2020, but it is already possible to hop on. The renovation progressed entirely according to plan. Only the definitive stop at the Amsterdam Zuid station is still a problem.
2Amsterdam is nearing completion. The INNSiDE hotel tower opens shortly, and the office tower will be ready mid-2021. We are now working on the Strawinskylaan immediately in front of buildings. During the night of 10 to 11 December we will apply the asphalt.
Residents are becoming concerned about the accessibility of the northern part of Verdi, which we intend to develop. They are worried that the area between de Schinkel and Amstelveenseweg will become too congested. Here are the answers to the four most frequently-asked questions.
During Whit weekend (8-10 June 2019), we will be putting the first part of the roof of the new Brittenpassage into position. But this mammoth task will be affecting travellers from as early as Friday, 10 May 2019. So what is all the work that needs to be done?