While the A10 Zuid motorway is closed from 22 July 2022 onwards we are going to be vibro driving 80 sheetpiles into the ground which are needed for the Brittenpassage excavation work later on. This work may cause noise pollution. We invite you to attend the drop-in meeting on Tuesday 5 July.
In Eduard van Beinumstraat, we are setting up a new construction site for the Zuidasdok project. This is needed for the renovation work on Amsterdam Zuid station. On it, we will be pre-building components for the second station passageway, the Brittenpassage.
From Saturday, 16 July until Friday 22 July, Line 52 (the North/South line) will not be running to and from Amsterdam Zuid station. During that time, we are doing construction work on two new, temporary metro platforms. This is a precision operation in an area the size of a postage stamp. So why are we doing it and how?