A glimpse inside low-vibration VU Research Building

The VU Research Building in De Boelelaan was completed in early 2024. It is an extraordinary building and the reason why only really becomes clear when you look inside it. ‘Even the tiniest vibrations and temperature differences can have an effect on measurements.’

Three-day trial for limited access to Minervapassage

On 16, 17 and 18 April 2024, we have closed off one of the two southern access tunnels of the Minervapassage. We are doing this in order to gain an impression of what will happen when the passageway is partially closed for a longer period from mid-2025.

Working in the ‘crawlspace’ of the Brittenpassage

The digging of the second passenger tunnel at Amsterdam Zuid station, the Brittenpassage, is now three-quarters of the way towards completion. Concrete trucks are currently in the process of creating a crawlspace. They are also preparing the foundations for the pillars that will support the roof of the passageway.

Night-time traffic disruption on A10 Zuid

In the evenings and nights between 27 and 30 March 2024, there will be works happening along the A10 Zuid in the Utrecht direction. This is expected to cause some disruption to traffic. In the night from Friday, 29 to Saturday 30 March, the S108 access road will be closed.

Parnassusweg closures for construction of metro viaduct

From April to July 2024, we are working on the metro viaducts across Parnassusweg. We are making preparations to enable the construction of a new viaduct there this summer. During this period, we will be closing the eastern carriageway (in the direction of the city) several times.

350 piles for additional station passageway

Piles, piles and even more piles. Under the roof of the second passenger tunnel at Amsterdam Zuid station, everything is focusing on foundation work. A total of around 350 piles are being inserted into the ground for the floor of the new Brittenpassage.

13 March: meeting about De Nieuwe Meer junction

In 2024, the reconstruction of the De Nieuwe Meer junction is set to start after a long period of preparation. At two walk-in meetings on Wednesday 13 March, we will give you an idea of the works you can expect in the years ahead and the related disruption.

Making space for A10 Zuid widening

At the start of March 2024, we will be removing trees and bushes at three locations around the De Nieuwe Meer junction. This will create space for work sites and access roads for construction. Ultimately, this will also enable the widening of the A10 Zuid. Cyclists will face some temporary disruption.

Summer 2024: reduced metro service at Amsterdam Zuid station

Between 7 July and 26 August 2024, the metros at Amsterdam Zuid station will run a modified service. Metros 50 and 51 will be using a single track instead of two, in both directions. The GVB's Ger Walstra tells us about it.
1

Philips headquarters nears completion

The completion of PI59, in Prinses Irenestraat, is in sight. In less than two years, the contractor has transformed the building from a brutalist bunker to an ultramodern Philips headquarters. It is a truly amazing transformation.

1 February: new Service & Tickets desk opens

On Thursday, 1 February 2024, the new GVB Service & Tickets desk in the existing passageway at Amsterdam Zuid station will open. The existing desk has to be removed to make space for the renovation of the passageway.

In the picture: four months of construction work on the Brittenpassage

The second passenger tunnel at Amsterdam Zuid station is beginning to take shape. In the space of four months, we have removed huge amounts of sand from underneath the A10, railway and metro tracks and the broad contours of the new passageway are now becoming visible. In this series of photos, we take a look back.