Night-time traffic disruption on A10 Zuid

In the evenings and nights between 27 and 30 March 2024, there will be works happening along the A10 Zuid in the Utrecht direction. This is expected to cause some disruption to traffic. In the night from Friday, 29 to Saturday 30 March, the S108 access road will be closed.

Parnassusweg closures for construction of metro viaduct

From April to July 2024, we are working on the metro viaducts across Parnassusweg. We are making preparations to enable the construction of a new viaduct there this summer. During this period, we will be closing the eastern carriageway (in the direction of the city) several times.

Eye to eye with the entryway to the Brittenpassage

The definitive entryways to the second passenger tunnel at Amsterdam Zuid station, the Brittenpassage, will not be in place until 2036. But when it opens in 2027, they will already be clearly recognisable, as a life-sized impression of the southern entrance shows.

In the picture: four months of construction work on the Brittenpassage

The second passenger tunnel at Amsterdam Zuid station is beginning to take shape. In the space of four months, we have removed huge amounts of sand from underneath the A10, railway and metro tracks and the broad contours of the new passageway are now becoming visible. In this series of photos, we take a look back.

Ground monitoring crucial when working under the rails

The renovation work at Amsterdam Zuid station involves working on and in a dike that is largely made of sand. Could the construction of the new Brittenpassage have an effect on that dike? The construction manager and a ground specialist explain.

Anti-graffiti tests for Amsterdam Zuid station

We have conducted tests to identify which coating and which removal product will be most effective in combating graffiti at the new Amsterdam Zuid station. We have found a product that most effectively meets our requirements.

One metro track closed due to minor subsidence

UPDATE 21 October, 13.00: Since early afternoon on 21 October, the 50 and 51 metro service from Amsterdam Zuid station in the direction of Amsterdam Central Station and Gein has resumed. We are now permanently monitoring the situation.

Dig-dig-dig for extra station passageway

After years of construction away from public view, the digging has started for the passenger tunnel at Amsterdam Zuid station: the Brittenpassage. We are removing 50,000 cubic metres of sand from underneath the A10, metro and railway tracks. And the site is spectacular to behold.

Be the first to walk through the new Brittenpassage

On Wednesday, 11 October 2023, we are organising something very special. For the first time ever, you have an opportunity to take a look around the additional passenger tunnel at Amsterdam Zuid station: the Brittenpassage. It promises to be an impressive journey underneath the A10, the trains and metros.

Reminder: A10 Zuid closed in the direction of Schiphol for two weekends

For two weekends in September 2023, there will be major traffic disruption on the south side of Amsterdam. Between 8 and 11 September and between 22 and 25 September, the A10 Zuid in the direction of Schiphol and The Hague will be closed from the Amstel interchange to the S108 VUmc access road.

Smooth shifting operation at Amsterdam Zuid in photos

On the evening of Wednesday, 9 August, it was finally time for the big event: shifting two sections of the roof for the Brittenpassage, the second passenger tunnel at Amsterdam Zuid station, into position millimetre by millimetre. It also attracted a great deal of interest from the press and public.

In photos: preparations for shifting operation at Amsterdam Zuid

On 7 and 8 August 2023, dozens of construction workers were working around-the-clock at Amsterdam Zuid station. Preparations were being made to move two huge roof sections for the second passenger tunnel – the Brittenpassage – into position. Take a look at what happened.