A10 closed for eight days ‘Good coordination will be crucial’

Construction manager Jeroen Monnik is responsible for installing the roof for the new station passageway at Amsterdam Zuid station in August 2023. We will be closing the A10 Zuid for eight days to enable it to happen. ‘Everything needs to be running again by 14 August.’

9 to 11 June: another diversion in station passageway

In the Minervapassage, the existing entrance to Amsterdam Zuid station, we are replacing the roof. In the evening of 9 June 2023, we will be moving a section of the new roof into position. This means that there will be another diversion in the passageway from 9 until 11 June.

9 June: Amsterdam Zuid station to get new roof

Starting on the evening of Friday, 9 June, Amsterdam Zuid station will be the scene of a spectacle. We are moving a gigantic section of the new roof for the station entrance – the Minervapassage – into position. And you can come and watch the operation in person. All you need to do is register.

Heavy precision work at Amsterdam Zuid station

Between 5 and 14 August 2023, the A4 and A10 Zuid will be closed in the direction of Utrecht. There will also be a reduced train service. In this period, we will be moving two roof sections into position for the additional passageway at Amsterdam Zuid station: the Brittenpassage. So, how are we doing this?

Parnassusweg closed for two weekends in city direction

Because of construction work, Parnassusweg will be closed to cars and buses travelling in the direction of the city in the last weekend of May and first weekend of June 2023. This will be followed in the summer by a two-month road closure for cars travelling out of the city.

Work starts to increase height of Amsterdam Zuid station passageway

On 5 May 2023, we started replacing the roof of the existing passageway at Amsterdam Zuid station. In the future, it will be much taller and wider than it is now. To make that possible, we demolished part of the existing roof. A photo report.

Successful meeting on Amstel interchange

On 5 April 2023, we spoke to around 75 residents, businesses and interested parties. It proved to be a very valuable meeting – we now have a clear picture of what the important topics are. In this article, we take a look at them.

Diversion in Minervapassage: 5 to 7 May

In the weekend of 5-7 May 2023, there will be a diversion in the Minervapassage, the existing passenger tunnel at Amsterdam Zuid station. This passenger tunnel will be much taller and wider in the future, which is why we are now demolishing part of the existing roof.

Concrete pouring for fifth roof section of Brittenpassage a success

On Wednesday, 12 April 2023, the concrete was poured for the fifth roof section of the new Brittenpassage. The logistics involved meant that there were numerous brief delays in Parnassusweg. Music and chocolate provided a welcome distraction during the waiting time.

120 concrete trucks on Parnassusweg cycle path and footpath

Cyclists and pedestrians using Parnassusweg on 12 April 2023 will need to watch out. They can expect significant disruption next to Amsterdam Zuid station caused by trucks transporting concrete. During the morning rush hour, we also planned to inject a little fun into the process.

Work on new Amsterdam Zuid station in April

In April, we are continuing our work on the regeneration of Amsterdam Zuid station. We will be inserting sheet piles into the ground and pouring concrete for the fifth roof section of the additional passenger tunnel, the Brittenpassage.

5 April: meeting on regeneration of Amstel interchange

On 5 April 2023, we are organising two walk-in meetings for residents, businesses and other interested parties in the future regeneration of the Amstel interchange by Zuidasdok. You are warmly invited to attend.