The VU Research Building in De Boelelaan was completed in early 2024. It is an extraordinary building and the reason why only really becomes clear when you look inside it. ‘Even the tiniest vibrations and temperature differences can have an effect on measurements.’
On 16, 17 and 18 April 2024, we have closed off one of the two southern access tunnels of the Minervapassage. We are doing this in order to gain an impression of what will happen when the passageway is partially closed for a longer period from mid-2025.
In the new Ravel residential district, something extraordinary is happening. To the south of the AFC football pitches, we are digging a canal: Ravelgracht. The fertile soil that we are removing is set to be reused in other places in Amsterdam.
The digging of the second passenger tunnel at Amsterdam Zuid station, the Brittenpassage, is now three-quarters of the way towards completion. Concrete trucks are currently in the process of creating a crawlspace. They are also preparing the foundations for the pillars that will support the roof of the passageway.
Alongside the 216 starter homes in Stepstone, Ceci is being built, a complex of 25 private sector apartments with a minimum size of 70 square metres. There will be commercial amenities on the ground floor. Ceci is scheduled for completion by the end of 2026.
In Beethovenstraat, Zadelhoff is developing the complex ‘The Harmony’, with 63 social rental homes and 85 mid-market rental homes. They will be part of the new Ravel residential district that is set to be built between the new AFC football pitches and De Boelelaan.
On 12 March 2024, more than 150 people visited the market in the Zuidas-Zuidasdok Information Centre. Alongside many familiar faces, there were also quite a lot of new ones. People with specific questions and people with a general interest in Zuidas and Zuidasdok.
In 2024, the reconstruction of the De Nieuwe Meer junction is set to start after a long period of preparation. At two walk-in meetings on Wednesday 13 March, we will give you an idea of the works you can expect in the years ahead and the related disruption.
At the start of March 2024, we will be removing trees and bushes at three locations around the De Nieuwe Meer junction. This will create space for work sites and access roads for construction. Ultimately, this will also enable the widening of the A10 Zuid. Cyclists will face some temporary disruption.
Although there will be nothing on sale, it will definitely be worth the effort coming along to our Information Centre in the WTC on tuesday 12 March 2024. At our market, you will have an opportunity to see, hear about and experience some of the major developments in your neighbourhood. You can even do some speed-dating.
The completion of PI59, in Prinses Irenestraat, is in sight. In less than two years, the contractor has transformed the building from a brutalist bunker to an ultramodern Philips headquarters. It is a truly amazing transformation.
The area between Kapel & Convict and the AkzoNobel and Stibbe buildings and the St. Nicolaaslyceum will be given a new layout in the next few years. The preliminary design for the public area is now ready. It is set to be green and park-like.